Hi,
Please see SMUD's responses below:
1. This project will require remote work only.
2. My apologies, but I do not see that in my version. The coverage per occurrence and in the aggregate should be $2M.
3. Yes, the scope of the roadmap will be focused on AMI and any equipment/technologies/systems/programs that use AMI as a foundational/enabling technology (including Grid Modernization). If the equipment/technologies/systems/programs do not utilize AMI as a foundation/enabling technology, they would be out of scope. Please review the detailed Project Deliverables in the Scope of Work section beginning on p. 2-3 of the RFP. This section includes details for what is expected for each Project Deliverable, including the “Finalize Scope for Roadmap” Deliverable.